Electrical engineer reviewing blueprints beside an industrial electrical panel

Hospital Lighting Conversion

San Fernando General Hospital | Trinidad and Tobago. A staged LED lighting upgrade across hospital corridors, covered access routes, and external areas.

Illuminated multi-story building at night with parked cars and vans in the foreground.
PROJECT EXPERIENCE

SWRHA LED Lighting Installation - 1M TT

Electrical engineer and project manager within the contractor's team, coordinating with SWRHA technical personnel on site requirements and lighting conversion decisions — including the 150 W cobra-head substitution, the directed conversion of 4 ft fluorescent fittings, and the closing engineering report.

Client

South-West Regional Health Authority (SWRHA)

Contractor

S. Persad Contracting Services Ltd.

Period

December 2024–June 2025 record period; physical works commenced February 2025 with staged implementation.

Outcome

Photographs document energised corridor, covered-route, and exterior lighting, delivered through technical review and staged close-out.

PROJECT GALLERY

Hospital Lighting Conversion

Energised corridors, covered routes, and exterior lighting across San Fernando General Hospital.

Exterior building lighting at night
Completed corridor lighting
Additional corridor lighting
Completed lighting installation
PROJECT 2 | NEW WING EXTENSION

12kV - 2.5MVA Transformer Replacement

San Fernando General Hospital — New Wing Extension. Status: Installed and tested — not commissioned.

MY ROLE IN PROJECT EXECUTION

How the work was executed

Working with S. Persad Contracting Services Ltd., I led installation planning and coordinated the specialist activities, focusing on transformer positioning, the HV/LV interfaces, and assessment of the existing electrical infrastructure. The transformer has been installed and tested; commissioning remains outstanding. I recommended replacement of the existing switchgear after it was found unable to be racked out.

1 | Installation planning

Defined the sequence of installation and testing, including lifting arrangements, equipment inspection, LV busbar alignment, and earthing.

2 | Coordination

Coordinated transformer positioning and the HV/LV interfaces, and liaised on the work needed to progress towards commissioning.

3 | Testing

Managed specialist transformer testing — insulation resistance / polarisation index, turns ratio, winding resistance, bolted-connection resistance, and an oil sample.

4 | A critical catch

Identified the existing switchgear's inability to rack out and recommended its replacement — a limitation that must be resolved before commissioning.

PROJECT GALLERY

Transformer Installation and Testing

Transformer positioning, HV/LV interfaces, and specialist testing.

Four electrical terminals labeled X1, X2, X3, and X0 inside a gray metal enclosure.
Technical nameplate for a 2500 kVA transformer manufactured by Jiangsu Yawei Transformer Co., Ltd.
Thick red industrial cable splitting into two white cables secured with black tape and insulation.
White crane lowering a large grey electrical transformer onto a flatbed truck near buildings.
BY THE NUMBERS

Numbers mean little. Code compliance means more.

Years behind a panel are only useful if the work passes inspection. You'll find what we've actually done, verified, and stood behind.

1

Engineer, One Standard

100%

Code-Compliant Work

Get a straight quote for your next project